Today, Gino was going to finish up the tile work in the guest bath. Unfortunately, when the drywall was put in around the sink area, instead of moving one of the pipes…the guys just screwed the greenboard in over the pipe causing it to bubble out. If we had done regular tile instead of butt joints, Gino would have been able to lay the tile over the bow and it wouldn’t have been a big deal but since all of the tiles are “butted up tight” against one another…it would have made for a bad tile job..so Gino spent a couple of hours chipping away at the greenboard and evening out the area with grout and didn’t have time to finish. So…still no toilet for us to use and no pictures for you to see. Once it is done, I’ll post the pictures so you can see how rad the travertine looks.
We bought all of our appliances at Sears today (summer is going to post pictures later) and met with our cabinet maker to tie him down to a price and time frame. More to come….